PK0-004 Exam Questions & Answers

Exam Code: PK0-004

Exam Name: CompTIA Project +

Updated: Sep 07, 2023

Q&As: 727

At Passcerty.com, we pride ourselves on the comprehensive nature of our PK0-004 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free CompTIA PK0-004 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your CompTIA PK0-004 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free CompTIA PK0-004 Dumps

Practice These Free Questions and Answers to Pass the CompTIA Project+ Exam

Questions 1

During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.

Which of the following is the MOST likely cause of these complaints?

A. The quality of the deliverable decreased due to the rising material cost.

B. The PM did not follow the project communication plan.

C. Quality assurance actions were not adjusted for the vendor change.

D. The change was not documented and approved.

Show Answer
Questions 2

A manager is reviewing some projects with two project managers who are working on the financial system. Which of the following BEST describes this type of review?

A. Operations

B. Project

C. Portfolio

D. Program

Show Answer
Questions 3

A functional manager within a project is requesting to edit the display features of an application that is being developed.

Which of the following has the authority to approve the edit?

A. PM

B. CCB

C. PMO

D. SME

Show Answer
Questions 4

Which of the following should be used to identify where slack is occurring in the project schedule and determine the critical path? (Choose two.)

A. PERT chart

B. Risk register

C. Arrow diagram method

D. RACI matrix

E. Project charter

F. Fishbone diagram

Show Answer
Questions 5

A testing event was held and deemed unsuccessful. After review, it becomes clear that the two project teams had different expectations of the testing.

Which of the following is needed between the two teams?

A. Communication plan

B. Project schedule

C. Status report

D. Use case

Show Answer