PK0-003 Exam Questions & Answers

Exam Code: PK0-003

Exam Name: CompTIA Project+ (2009)

Updated: Apr 23, 2024

Q&As: 320

At Passcerty.com, we pride ourselves on the comprehensive nature of our PK0-003 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free CompTIA PK0-003 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your CompTIA PK0-003 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free CompTIA PK0-003 Dumps

Practice These Free Questions and Answers to Pass the CompTIA Project+ Exam

Questions 1

Which of the following is the primary purpose of a WBS?

A. To track project milestone completions

B. Show project tasks scheduled for a specific time period

C. Decomposition of the project deliverables

D. Assign specific tasks to project team members

Show Answer
Questions 2

Schedule dependencies include: (Select TWO).

A. Successor activities

B. Risks

C. Constraints

D. Predecessor activities

E. Issues

F. Assumptions

Show Answer
Questions 3

After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The project manager MUST:

A. Update the risk register.

B. Implement the change.

C. Cancel the project.

D. Generate a change request.

Show Answer
Questions 4

Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select THREE).

A. Time zones

B. Travel costs

C. Co-location of resources

D. The project plan

E. Scheduled vacations

F. Language barriers

Show Answer
Questions 5

Which of the following would be included in the project transition plan?

A. Specifications used for quality control measurements.

B. Comparison of project deliverables with organizational strategic goals.

C. Maintenance responsibilities of the project deliverables.

D. Analysis of the project expenditures.