JK0-017 Exam Questions & Answers

Exam Code: JK0-017

Exam Name: CompTIA E2C Project+ Certification Exam

Updated: Apr 26, 2024

Q&As: 402

At Passcerty.com, we pride ourselves on the comprehensive nature of our JK0-017 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free CompTIA JK0-017 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your CompTIA JK0-017 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free CompTIA JK0-017 Dumps

Practice These Free Questions and Answers to Pass the CompTIA Project+ Exam

Questions 1

In which of the following organization types would a project manager have the MOST authority?

A. Projectized

B. Balanced Matrix

C. Weak Matrix

D. Functional

Show Answer
Questions 2

One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation?

A. Ask other team members to help.

B. Assign the team member to another project.

C. Talk to the team member to encourage better performance.

D. Arrange for training for the team member.

Show Answer
Questions 3

The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?

A. $35,624.00

B. $59,373.33

C. $71,248.00

D. $85,497.60

Show Answer
Questions 4

When would a project manager have a closure meeting? (Select Three).

A. Stage completion

B. Task completion

C. Document completion

D. Project cancellation

E. Project completion

F. Vendor cancellation

Show Answer
Questions 5

The initiation process concludes with the creation of which of the following?

A. Contingency reserve

B. Project charter

C. Project schedule

D. Project scope statement