HPE6-A49 Exam Questions & Answers

Exam Code: HPE6-A49

Exam Name: Aruba Certified Design Expert 8 Written Exam

Updated: May 03, 2024

Q&As: 60

At Passcerty.com, we pride ourselves on the comprehensive nature of our HPE6-A49 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free HP HPE6-A49 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your HP HPE6-A49 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free HP HPE6-A49 Dumps

Practice These Free Questions and Answers to Pass the Aruba Certified Design Expert (ACDX) V8 Exam

Questions 1

A customer has multiple medium and large branch sites, each of which requires between 8 and 16 APs and supports between 200 and 600 wireless clients. Every branch site has an internet connection, which it uses to reach the central data center. The customer would prefer the WAN links to be optimized in the solution. Each side handles between 1 and 2 Gbps of traffic, most of which goes to the central data center. The data center has 7210 controllers for terminating the VPN connections.

Which branch office solution best meets the customer needs?

A. CAPs and branch office controllers with an SD-WAN license

B. IAPs and no branch office controllers

C. CAPs and branch office controllers

D. RAPs and no branch office controllers

Show Answer
Questions 2

Refer to the exhibit.

A writing closet needs to support these devices: 100 desktops 5 printers 20 AP-345s

The customer wants to single-home the AP-345s and support higher than 1GbE speeds on the AP connections to future proof. The customer also requires that the closet have two 10GbE links to the core with SR transceivers. The exhibit shows the preliminary plan for this closet.

Which correction should the architect make to the plan to meet the customer requirements?

A. Change all of the switches to the Aruba 2930M 40G 8 HPE Smart Rate PoE+ 1-Slot Switch.

B. Change one switch to the 2930M 24-port Smart Rate PoE+ model.

C. Add a 4-port SFP+ module to one of the switches.

D. Add a Smart Rate module to each of the switches.

Show Answer
Questions 3

Refer to the exhibit.

An architect needs to design the topology for a new wired network at a campus with three buildings. The exhibit above shows the cabling layout. The customer requires link redundancy at all layers, up to one switch-to-switch link can fail without an effect on client connectivity. The architect has determined that the closet of each floor should have three Aruba 2930M switches, and the core will use Aruba 5406 switches. The aggregation layer, if used, will use Aruba 3810M switches. However, the customer prefers the elimination of the aggregation layer and has asked the architect to advise the impact of the elimination of this layer.

Where would the elimination of the aggregation layer require rewriting?

A. All of the buildings

B. Building 1 and Building 2 only

C. Building 1 and Building 3 only

D. Building 3 only

Show Answer
Questions 4

In which of these scenarios do the customer requirements point towards tunneled node, or dynamic segmentation, on AOS-Switches?

A. A customer has wired IoT devices and wants to be able to control their access. The architect recommends sending all of their traffic through the MC role-based firewall.

B. A customer wants to manage their AOS-Switches in a more centralized manner. They would like to connect AOS-Switches to AirWave over secure IPsec tunnels and control all configuration from there.

C. A customer has a branch office with an AOS-Switch and an Internet connection. The customer would like to give branch office users secure access to the corporate LAN over an IPsec tunnel.

D. A customer lacks physical security and wants to impose 802.1X authentication on wired ports. After employees complete 802.1X authentication, they should receive full access to the network.

Show Answer
Questions 5

A writing closet needs to support 20 APs and 110 wired endpoints. It has four strands of OM3 fiber to the network core 150 feet (45 m) away. The customer wants the links to the network core to support at least 10GbE. The customer also requires no loss in connectivity for the switches in the closet, even with the loss of one link. The architect plans to recommend three 2930M 40G 8SR PoE+ switches, two 4-port SFP+ modules, and two SFP+ SR transceivers.

What should the architect change about the plan?

A. Add three 10GbE direct attach cables (DACs) or three stacking cables.

B. Add a stacking module for each switch and three stacking cables.

C. Change the two SFP+ SR transceivers to SFP+ LRM transceivers.

D. Add one 4-port SFP+ module and one SFP+ SR transceiver.

Show Answer