Exam Code: CCE-CCC

Exam Name: Certified Cost Consultant / Cost Engineer (AACE International)

Updated:

Q&As: 115

At Passcerty.com, we pride ourselves on the comprehensive nature of our CCE-CCC exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free Test Prep CCE-CCC Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your Test Prep CCE-CCC exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free Test Prep CCE-CCC Dumps

Practice These Free Questions and Answers to Pass the Test Prep Certifications Exam

Questions 1

Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.

A. Directive listening

B. Non-listening

C. Visual listening

D. Facilitative listening

Show Answer
Questions 2

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What information is needed to develop a Class 2 definitive estimate?

A. Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates

B. Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs

C. Square footage of facilities, factored indirects and home office costs

D. Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied

Show Answer
Questions 3

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are:

A. Marginal profits

B. Lost profits

C. Incurred profits

D. Postponed profits

Show Answer
Questions 4

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

A. $31,875

B. $12,550

C. $29,600

D. $13,515

Show Answer
Questions 5

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last

twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be

$22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

You have been asked to provide ETC information to management. Based on the following information,

what is the ETC?

Original Budget = $9,000,000

Actuals to date = $3,513,000

Current estimate at completion = $10,613,000 Actuals for current month = $1,200,000

A. $10,613,000

B. $9,000,000

C. $5,487,000

D. $7,100,000

Show Answer