PR2P Exam Questions & Answers

Exam Code: PR2P

Exam Name: Exin PRINCE2 Practitioner (PR2P)

Updated: Apr 12, 2024

Q&As: 190

At Passcerty.com, we pride ourselves on the comprehensive nature of our PR2P exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free EXIN PR2P Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your EXIN PR2P exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free EXIN PR2P Dumps

Practice These Free Questions and Answers to Pass the Exin Certification Exam

Questions 1

HOTSPOT Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.

Drop down the right answer from column 1 to column 2.

Hot Area:

Show Answer
Questions 2

Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes: There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including: 20% discount for all repeat customers - not cost-effective and very short term A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year A series of television and press advertisements· was too expensive A direct mail shot to all customers - benefit would be short term Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Which 2 statements should be recorded under the Timescale heading?

A. Benefits will be lost if the project is not completed on time.

B. A recruitment campaign to fill the existing staff vacancies will need to take place in the next 12 months.

C. Additional 10% increase in orders in year two.

D. The prepared calendar pack must be delivered by the first week in December.

E. The print company requires a 2 week notification period of the calendar pack delivery.

Show Answer
Questions 3

Scenario Additional Information Product Description

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff

before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products

will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1.

This document defines the approach to be taken to achieve the required quality levels during the project.

2.

The Project Board will have overall responsibility for the Quality Management Strategy.

3.

Project Assurance will provide assurance on the implementation of the Quality Management Strategy. Quality management procedure - Quality standards

4.

The selected service provider will operate to industry standards for providing outsourced services.

5.

MFH document standards will be used.

Records

6.

A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7.

Configuration Item Records will be maintained for each product to describe its status, version and variant.

8.

Approval records for products that require them will be stored in the quality database. Roles and responsibilities

9.

The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10.

Team Managers will provide details of quality checks that have been carried out.

11.

Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12.

The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Although it is not specified in the current corporate branding standards, the MFH corporate logo should be shown on the front page of the service level agreement.

A. Obtain agreement from the Director of Facilities Division to amend this within the remaining +2 days tolerance.

B. Raise an issue (off-specification).

C. Raise an issue (request for change).

D. Accept this error as a concession.

Show Answer
Questions 4

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being

monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the

impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response.

The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's

calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under either the Records or Reporting headings?

A. Project Support will maintain the Risk Register.

B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.

C. The Change Authority will report monthly to the Project Manager on the status of the change budget.

D. Risks that are likely to occur within the next two weeks should be recorded as imminent.

E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.

Show Answer
Questions 5

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being

monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the

impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response.

The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's

calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Timing of risk management activities heading?

A. During stage 4, the selected service provider will manage any risks to their Business Case and report these to the Project Manager on a weekly basis.

B. The Project Board should hold monthly meetings to review project progress.

C. When closing a project, the follow-on action recommendations should be updated with any risks relating to the realization of benefits after the outsourced services go live.

D. Any new risks identified during product development should be reported to the Project Manager by the Team Manager when delivering the completed Work Package.

E. When authorizing a stage, the Project Board will check that the exposure to risk is still acceptable.

Show Answer

Viewing Page 1 of 3 pages. Download PDF or Software version with 190 questions