Exam Code: CAT-241
Exam Name: CA Clarity PPM v13.x Business Analyst
Updated: Mar 22, 2024
Q&As: 50
At Passcerty.com, we pride ourselves on the comprehensive nature of our CAT-241 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.
Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your CA CAT-241 exam.
Instant download
Latest update demo according to real exam
You have developed a new process and transported it to a production environment using XML Open Gateway (XOG). To make the process operational, which step do you need to perform?
A. Change Mode to Active.
B. Validate the process only.
C. Run the Execute a Process job.
D. Validate and activate the process.
When you use a partition model, which objects are configurable to a specific partition? (Choose two)
A. Report
B. Project
C. Timesheet
D. Application
When you use the Assign Resources page to assign a new resource to a project, you notice a resource that is no longer available for your project. You are unable to remove the resource because it has already booked actuals for a task. Which option is available to you?
A. Remove the resource from your team and then remove the resource.
B. Deactivate the resource and delete the resource when the project is completed.
C. Set the Estimated Time to Complete (ETC) to zero and then remove the resource.
D. Click Replace and assign another resource to take on the remaining work from the original resource.
When you create a scenario, which guideline should you follow?
A. If any field appears in read-only mode, double-click it to make it editable.
B. Avoid adding investments if you do not intend to make what-if changes to them.
C. If you add investments that are not included in the portfolio, make sure to approve them.
D. To prevent error messages, always begin by populating the Planned Cost and Planned Benefit fields.
What is a valid reason to use the Transaction Entry functionality?
A. Modify existing transactions.
B. View the pro forma invoice for a customer.
C. Enter additional transactions to the system that were not entered through timesheets.
D. View the data from timesheets that have been posted through the Post to Financials job option.
Viewing Page 1 of 3 pages. Download PDF or Software version with 50 questions