BH0-007 Exam Questions & Answers

Exam Code: BH0-007

Exam Name: ISEB Intermediate Certificate in Software Testing

Updated: Apr 16, 2024

Q&As: 25

At Passcerty.com, we pride ourselves on the comprehensive nature of our BH0-007 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free ISEB BH0-007 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your ISEB BH0-007 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free ISEB BH0-007 Dumps

Practice These Free Questions and Answers to Pass the ISEB Certification Exam

Questions 1

Which of the following is an accurate depiction of the hierarchy of test management documentation (where the highest comes first)?

A. Test policy-Test strategy-Project test plan-System test plan

B. Test strategy-Test policy-Project test plan-System test plan

C. Test policy-Project test plan-Test strategy-System test plan

D. Project test plan-Test strategy-System test plan-Test policy

Show Answer
Questions 2

Which of the following methods of test estimation would be most appropriate for each Sprint?

A. Ask the testers to talk to each other and reach a consensus.

B. Take 30% of the total development time required for the Sprint.

C. Conduct a test point analysis on the content and navigation requirements.

D. Use metrics from the last accessibility project at MSC.

Show Answer
Questions 3

Which of the following reviews would you recommend to address this issue?

A. A walkthrough of the requirement specification, to check for errors.

B. A management review of defects logged and cleared to see if defects are being addressed correctly.

C. A technical review of the industry standard routing protocols to see if they have inaccuracies in them.

D. An inspection of the code for this part of the functionality to try to localise the defective parts of the code.

Show Answer
Questions 4

Which one of the following test tools would you recommend for the E2E phase.

A. A configuration management tool to ensure that all user-stories have been properly archived.

B. A test design tool to create the test cases as efficiently as possible.

C. A performance test tool to check that anticipated loading can be handled.

D. A modelling tool to verify the stock exchange pricing structures.

Show Answer
Questions 5

Which two of the following measures would give the best indication of likely product quality?

a.

Number of hours of overtime worked.

b.

Number of test runs.

c.

Coverage of requirements achieved.

d.

Defect trends. e.Budget sent so far.

A.

a and c.

B.

b and d.

C.

c and d.

D.

a and d.

Show Answer

Viewing Page 1 of 3 pages. Download PDF or Software version with 25 questions