1Z0-567 Exam Questions & Answers

Exam Code: 1Z0-567

Exam Name: Primavera P6 Enterprise Project Portfolio Management 8 Essentials

Updated:

Q&As: 84

At Passcerty.com, we pride ourselves on the comprehensive nature of our 1Z0-567 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free Oracle 1Z0-567 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your Oracle 1Z0-567 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free Oracle 1Z0-567 Dumps

Practice These Free Questions and Answers to Pass the Oracle Partner Network Exam

Questions 1

Identify the true statement regarding Activity Step templates.

A. Activity % complete must be Physical when using Activity Step templates.

B. There are limits to the number of Activity Step templates in the database.

C. Activity Step templates are the place where resources are allocated and assigned.

D. Activity Step Templates are governed by global security.

Show Answer
Questions 2

Identify this icon:

A. Customize Columns in the View

B. Customize Tabs in the Details

C. Customize GANTT Chart Options

D. Customize and Save View

Show Answer
Questions 3

You are a project manager managing a large construction project. One of the pieces of heavy equipment required to dig the Foundation will most likely not be available until a specific date, because that equipment has been allocated to another, higher priority project. In that related project schedule you clearly see that in all likelihood, the activity in that plan that uses that equipment will also slip. You want to reflect this in your project schedule using a constraint.

What would be the most appropriate constraint to use?

A. Start On

B. Start On or Before

C. Start On or After

D. Mandatory start

Show Answer
Questions 4

This graphic is an example of a ___________.

A. spreadsheet

B. scorecard

C. portfolio

D. waterline analysis

Show Answer
Questions 5

You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?

A. Your security does not allow you to update Activity Status.

B. You did not save the changes made to the activities.

C. You have not completed each of the activity steps.

D. You must refresh the view in the web to view the changes.

Show Answer

Viewing Page 1 of 3 pages. Download PDF or Software version with 84 questions