ISSMP Exam Questions & Answers

Exam Code: ISSMP

Exam Name: ISSMP:Information Systems Security Management Professional

Updated:

Q&As: 224

At Passcerty.com, we pride ourselves on the comprehensive nature of our ISSMP exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free ISC ISSMP Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your ISC ISSMP exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free ISC ISSMP Dumps

Practice These Free Questions and Answers to Pass the ISC Certification Exam

Questions 1

SIMULATION

Fill in the blank with the appropriate phrase. ____________ is the ability to record and report on the configuration baselines associated with each configuration item at any moment of time.

Show Answer
Questions 2

Which of the following types of activities can be audited for security? Each correct answer represents a complete solution. Choose three.

A. Data downloading from the Internet

B. File and object access

C. Network logons and logoffs

D. Printer access

Show Answer
Questions 3

You are a project manager of a large construction project. Within the project you are working with several vendors to complete different phases of the construction. Your client has asked that you arrange for some of the materials a vendor is to install next week in the project to be changed. According to the change management plan what subsystem will need to manage this change request?

A. Cost

B. Resources

C. Contract

D. Schedule

Show Answer
Questions 4

Which of the following access control models uses a predefined set of access privileges for an object of a system?

A. Role-Based Access Control

B. Mandatory Access Control

C. Policy Access Control

D. Discretionary Access Control

Show Answer
Questions 5

Which of the following statements about the availability concept of Information security management is true?

A. It determines actions and behaviors of a single individual within a system.

B. It ensures reliable and timely access to resources.

C. It ensures that unauthorized modifications are not made to data by authorized personnel or processes.

D. It ensures that modifications are not made to data by unauthorized personnel or processes.

Show Answer

Viewing Page 1 of 3 pages. Download PDF or Software version with 224 questions